Project Management Professional (PMP)® Certification Exam
Independent PMP® Practice Exam
This independent PMP practice exam follows the July 2026 Examination Content Outline from the Project Management Institute (PMI®), the one in force for every exam scheduled on or after July 9, 2026. The exam is 180 questions (170 scored, 10 pretest) in 4 hours, across three domains: People 33%, Process 41% and Business Environment 26%. The free diagnostic opens when this bank is published.
The free PMP diagnostic is being prepared and is not open yet. The exam facts and the content outline on this page are current.
The outline changed in July 2026, and the weights moved a long way. Under the outline it replaced, Business Environment was 8% of the exam; it is now 26%. People went from 42% to 33% and Process from 50% to 41%. The length changed too: the retired exam was 230 minutes with 175 scored questions, and the current one is 240 minutes with 170. Material built for the old outline under-prepares you for more than a quarter of the current exam.
PMP questions are situational. They describe a project, a team and a problem, and ask what the project manager should do. Several options are usually things a project manager might reasonably do, which is why each question here explains all of them: the reason an option is second-best is the thing to learn.
PMP exam facts: questions, time limit, cost and passing score
What you are preparing for, in the exam owner's own numbers.
| Questions | 180 (170 scored, 10 unscored) |
|---|---|
| Time limit | 4 hours |
| Delivery | Computer-based through Pearson VUE: in person at a test center (PMI's recommended option) or online proctored (OnVUE). One 240-minute clock with two 10-minute breaks; answers cannot be revisited after a break. Some interactive question types appear only at test centers. |
| Eligibility | One of four education and experience routes, all within the last 10 years: secondary diploma plus 60 months leading projects, associate-level qualification plus 48 months, bachelor's degree plus 36 months, or a PMI GAC-accredited degree plus 24 months. Also 35 hours of project management training, waived for active CAPM® holders. |
| Passing standard | PMI does not publish a passing score. The standard is set by psychometric analysis against defined criteria, and the result is reported as pass or fail with diagnostic performance information. |
| Retakes | Up to three attempts within the one-year eligibility period, with the exam fee paid again for the second and third attempts. After three failures the candidate must wait one year from the last attempt before reapplying. |
| Outline in force | PMP Examination Content Outline – July 2026 (© 2026 PMI), effective July 9, 2026 |
Exam facts are taken from PMI’s own published material, last checked . Source. Confirm fees, dates and rules with the organization you register with before you book.
Who takes it
Experienced project leads. PMI offers four routes to eligibility, each needing experience within the last 10 years: a secondary diploma plus 60 months leading projects, an associate-level qualification plus 48 months, a bachelor's degree plus 36 months, or a PMI GAC-accredited degree plus 24 months. All four also need 35 hours of project management training, which is waived for active CAPM® holders.
What is on the PMP exam? Domains and weights
3 content areas and the share of the exam each carries. The bank is tagged to the same outline, so your results come back by area.
| Domain | Weight | What it covers |
|---|---|---|
| IPeople8 tasks | 33% |
All 8 People tasks
|
| IIProcess10 tasks | 41% |
All 10 Process tasks
|
| IIIBusiness Environment8 tasks | 26% |
All 8 Business Environment tasks
|
Key PMP concepts to know
People: leading the team and handling conflict
- Tuckman's stages of team development run forming, storming, norming, performing and adjourning. A new team arguing over roles is in storming; the fix is clarifying roles and ground rules, not replacing members.
- Collaborating, or problem solving, is the conflict approach that produces a lasting result because it addresses the cause. Forcing settles things fast but wins one side; smoothing and withdrawing only postpone the conflict.
- Servant leadership means removing impediments, shielding the team from distractions and coaching rather than directing. On an agile team the project manager facilitates and lets the team decide how to do its work.
- Ground rules are agreed by the team and enforced by the team. A first breach is handled privately and directly with the person, not by escalating to their functional manager.
- Knowledge transfer has two forms: explicit knowledge that can be written down, such as a lessons learned register, and tacit knowledge such as judgment, which passes through mentoring, pairing and conversation.
People: stakeholders and communication
- Stakeholder identification starts at the beginning of the project and continues throughout. The stakeholder register records who they are; the engagement plan says how to move each from their current to their desired level of engagement.
- A power/interest grid sorts stakeholders: manage closely those with high power and high interest, keep satisfied those with high power and low interest, keep informed those with low power and high interest, and monitor the rest.
- Communication channels grow fast with team size: n(n - 1) / 2. A team of 10 has 45 channels; adding 5 people makes 105.
- Push communication (email, memos) sends information out; pull communication (a shared site, a repository) lets people fetch it; interactive communication (meetings, calls) is best for resolving misunderstanding.
- When a stakeholder disagrees with the project vision, first understand their concern directly, then align expectations. Going over their head is rarely the answer.
Process: approach, scope and schedule
- Predictive approaches plan scope up front and control change; adaptive approaches deliver in short iterations and expect requirements to evolve; hybrid mixes the two. PMI's outline puts about 60% of questions on adaptive or hybrid work.
- The WBS breaks the total scope into deliverables down to work packages. The 100% rule: the levels below an element must add up to all of its work, and nothing outside scope.
- The critical path is the longest path through the network and sets the shortest possible project duration. Activities on it have zero total float; delaying one delays the finish.
- Total float is late start minus early start. Crashing adds resources to critical activities and raises cost; fast tracking overlaps activities in parallel and raises risk.
- In Scrum, the product owner orders the backlog, the developers decide how to build the increment and the scrum master coaches the process. A sprint is fixed-length, one month or less.
Process: cost, earned value and procurement
- Earned value terms: PV is the planned value of work scheduled, EV the value of work actually done, AC the actual cost of that work. BAC is the total budget.
- Cost variance CV = EV - AC and schedule variance SV = EV - PV; negative means over budget or behind schedule. CPI = EV / AC and SPI = EV / PV; below 1.0 is bad.
- Estimate at completion, if current cost performance continues, is EAC = BAC / CPI. Estimate to complete is ETC = EAC - AC, and variance at completion is VAC = BAC - EAC.
- Contingency reserve covers identified risks and sits inside the cost baseline; management reserve covers unknown unknowns, sits outside the baseline, and needs management approval to use.
- Fixed-price contracts put cost risk on the seller; cost-reimbursable contracts put it on the buyer; time and materials sits between and suits small or uncertain work.
Process: quality, resources and closing
- Cost of quality splits into the cost of conformance (prevention, appraisal) and the cost of nonconformance (internal and external failure). Preventing defects is cheaper than finding them, and finding them is cheaper than a customer finding them.
- Quality assurance improves the process; quality control inspects the product. Validating scope is the customer formally accepting deliverables that have already passed quality control.
- In agile work, the definition of done is the team's shared checklist for any increment, while acceptance criteria apply to a single backlog item.
- Closing a project or phase means confirming acceptance against the agreed criteria, handing over deliverables, closing contracts, releasing resources and archiving lessons learned. Skipping formal acceptance is a common wrong option.
Business Environment: governance, change, risk and compliance
- In a predictive project, a change request is assessed for its impact on scope, schedule, cost and risk before it goes to the change control board. The project manager does not approve or reject it alone.
- In an adaptive project, new requirements go to the product owner, who orders them in the backlog. That is the change process, not a breach of it.
- Threat responses: escalate, avoid, transfer, mitigate, accept. Opportunity responses: escalate, exploit, share, enhance, accept. Buying insurance transfers a threat; it does not remove it.
- A risk is uncertain and in the future; an issue has already happened. When a risk occurs, it moves to the issue log and the planned response is carried out.
- Governance sets escalation paths and thresholds in advance. A variance inside the project manager's tolerance is handled by the project manager; one beyond it is escalated as the governance plan says.
- Organizational change needs a plan for the people affected: assess the culture and readiness, communicate the reason for the change, and support adoption after handover.
Common PMP exam mistakes and how to avoid them
Escalating to the sponsor before the project manager acts
Most scenarios expect you to analyze the situation and act within your own authority first. Escalate only when the problem exceeds your tolerances or authority.
Approving a change request yourself because it looks small
In predictive work, assess the impact and route it through integrated change control. Even a free change can affect risk or quality.
Answering agile scenarios with a predictive mindset
About 60% of questions reflect adaptive or hybrid approaches. On an agile team, favor options where the team self-organizes and the product owner decides priority.
Flipping the earned value formulas
Every variance and index starts with EV: CV = EV - AC, SV = EV - PV, CPI = EV / AC, SPI = EV / PV. Write them down before you start.
Picking the right action at the wrong time
Read for words such as first, next and best. Gathering facts or reviewing the plan usually comes before a corrective action.
Leaving flagged questions for later in the exam
After each of the two breaks you cannot return to earlier questions, so review your flags at the end of every block.
How to study for the PMP exam with practice tests
- 1
Check all three domains before you plan
Start with a mixed set weighted like the exam. If you studied from older material, look at Business Environment first: it is where the outline grew most.
- 2
Practice choosing between good options
In tutor mode, commit to an answer and a reason before reading the explanation. If your answer was right for the wrong reason, treat it as a miss.
- 3
Train for the breaks as well as the clock
The exam is one 240-minute clock with two 10-minute breaks, and you cannot return to earlier answers after a break. Practice in three blocks and close each one before you stand up.
- 4
Sit a full-length practice exam
180 questions in 4 hours. PMI allows three attempts within your one-year eligibility period and charges the exam fee again for the second and third, so practice is the cheap place to find out you are not ready.
What is in the paid PMP bank
The question bank
The PMP bank is still being written. The live count appears here when questions are published.
Every option explained
A written reason for every option, right and wrong, plus a one-line takeaway, a cited reference and the outline task the question tests.
Tutor mode and timed mode
Tutor mode shows the explanation after each question. Timed mode holds everything back until the end, at exam pace.
A readiness band, by domain
Your first-attempt results weighted the way the exam weights its domains, shown as a band rather than a pass probability: nobody outside the exam owner knows the cut score.
A study plan
Set your exam date and the plan divides the questions you have not seen across the days you have left, weakest domains first.
How the questions are written and checked
Step 1
Written to the public outline
Each question is written by AI against one task in PMI's published content outline. Nothing is taken from the exam itself.
Step 2
Solved blind by a second model
A different model answers the question without seeing the key. If it does not reach the same answer, the question is not published.
Step 3
Audited for flaws and duplicates
A separate pass looks for item-writing flaws: two defensible answers, a giveaway in the wording, a rationale that contradicts the key. Near-duplicates are removed.
Step 4
Corrected in public
Learners can report any question. Reports and answer statistics flag questions for withdrawal or correction, and every correction is logged.
There is no human subject-matter-expert review in that process, and we do not claim one. What you get instead is a cited reference on every question, so you can check it yourself. Read the full methodology or see the corrections log.
PMP practice exam FAQ
What are the common questions asked in the PMP exam?
Situational ones. Most PMP questions describe a project, a team and a problem and ask what the project manager should do next, with several options a project manager might reasonably choose. PMI also uses multiple-response, case or scenario sets, graphic-based, matching, pull-down and point-and-click questions; PMP sample questions in each format are worth practicing before test day.
What is the best practice exam for the PMP exam?
One written to the July 2026 Examination Content Outline, which PMI uses for every exam scheduled on or after July 9, 2026: People 33%, Process 41% and Business Environment 26%, 180 questions in 4 hours. Material built for the 2021 outline gives Business Environment 8% and under-prepares you for more than a quarter of the current exam.
What is the best mock exam for the PMP exam?
A full-length one under the real conditions: 180 questions on one 240-minute clock, with two 10-minute breaks and no returning to earlier questions after a break, weighted to the July 2026 outline. Sit at least one such PMP mock exam in three blocks before you book.
How many people fail the PMP?
PMI does not say: it publishes neither a pass rate nor a passing score, so any failure figure you see quoted is an estimate. What PMI does publish is the retake rule: three attempts within your one-year eligibility period, with the exam fee paid again for the second and third.
Is this PMP practice exam free?
Not yet. This site's free PMP diagnostic opens when the bank is published. After that, the full bank and timed mode are part of a paid pass, charged once and never renewed.
Is this PMP practice exam on the 2026 outline?
Yes. The PMP practice questions here are written to PMI's July 2026 Examination Content Outline, with People 33%, Process 41% and Business Environment 26%, and the full-length format is 180 questions in 4 hours. They are original questions, not PMI exam questions.